GASYEAR

Recognised by the OPM Flow parserSCHEDULE

This keyword advances the simulation over one or more gas contract years for when the Gas Field Operations option has been activated by the GASFIELD keyword in the RUNSPEC section. A contract year in this case is the period over which the Daily Contract Quantity is fixed, this can a be year, this keyword or the GASPERIO keyword in the SCHEDULE section, or one or more months. If the contract period is over one or more months then the GASPERIO keyword in the SCHEDULE section can be used instead of GASYEAR.

GASYEAR is an alternative to the DATES, TIME and TSTEP keywords in the SCHEDULE section that advances the simulation to a given report time after which additional keywords may be entered to instruct OPM Flow to perform additional functions via the SCHEDULE section keywords.

This keyword is not supported by OPM Flow but would change the results if supported so the simulation will be stopped.

Records
Fixed number of records
Record count
1
Items per record
8

Parameters

No.NameDescriptionTypeDimensionDefault
1NUM_YEARSINT
2INITIAL_DCQDOUBLE
3SWING_REQSTRINGYEAR
4LIMIT_TIMESTEPSSTRINGYES
5LIMIT_DCQ_RED_FACTORDOUBLE10
6ANTICIPATED_DCQ_RED_FACTORDOUBLE11
7MAX_ITERATIONSINT3
8DCQ_CONV_TOLERANCEDOUBLE10.1

Manual source: parts/chapters/subsections/12.3/GASYEAR.fodt